I went to rebuild a complete kitchen last year with an entrepreneur. Here are the things in the order of events

1. Booting old appliances, cabinets, flooring, and a whole wall.
2. Rough plumbing sectors.
3. Electrical work.
4. Cabinets set.
5. Installing granite.
6. Installing a marble floor.
7. Bring on the devices.
8. Plumbing connections.

Make sure you have good plans for his cabinet that the mandate of the rough plumbing and electrical before Company shall enter into force brought

cleocat said...

Rip It Out
Plumbing
Electrical
Plastering
Replace
Decoration
It's just like us, but the company has its own routine, I suppose

ne11 said...

You need a permit. Draw a diagram of the kitchen, so you can plan on the position of the new cabinets and island. Rental of plumbing and electrical suppliers. Order the new cabinets, sinks, floors, countertops, appliances, etc. Rent a Dumpster.

Hold down the sink, refrigerator and oven at the same place, unless you know how to move or extend plumbing lines. When you move a gas stove, you need to move the call to the Power Company gas pipeline.

Removed after removing the old kitchen, otherwise the first walls. If you do not add more space, not for cooking, you can not possibly replace the rock on the page. Color of the ceiling. Paint walls and woodwork, where appliances and cabinets to go first.

Install cabinets, a sink and surfaces. Install extractor fan and lighting. Set up large appliances. Call a plumber to install, the sink and connect the ice machine in the fridge. All bathrooms and kitchens should switch points of leakage and earth. Call an electrician to do this task.

Finish paint walls and trim. Since he did not specify the nature of the soil, this step-May not be justified. Vinyl, wood or laminate flooring will be installed shortly. Install tile floors next.

You did not mention if you change the windows or doors. If you hire a professional. Of course, this step comes before the preparation of the walls.

Touch up paint on. Dust extraction and clean the counters, etc., as you work. Add windows and decorative elements.

Remember to measure everything twice in order to avoid costly mistakes. Security practices through the use of goggles to protect your eyes.

chizzy said...

U should ask a professional.

chizzy said...

U should ask a professional.

Hoodoo said...

First, you want to sum up what you can afford to maintain and what is the best in his area of your budget. I want to go somewhere like the IFM have different ideas and allow you to monitor products in stock to see if they are to your taste. Then they give you all planning a set and go from there. I want to make a lot of research on Google first one!

magiclad... said...

BNQ Wickes or somewhere Conatact a free survey with a plan and costing. After up to you to decide to use its merchant fleet or your own

arethusa... said...

The correct order is:
Think about it, (change of mind) is cheaper now than later.
Buy or take over all the parties (not to play.)
Starting the old stuff as the night near the fire as possible.
Sort all plumbing, electrical and field work.
Insert the new units.
Connect plumbing equipment, a man qualified for the electrical system here.
Solution of the plaster and roof tiles.
Smack the wrist of a woman who believes it is time for a vase of flowers lay on the table again, make an infusion of coffee and sit on the floor drinking and admiration for the work, while everyone knows the password to the other to buy new chairs. After going outside, and a grid instead of the pollution of the new kitchen ...
.......................... Enjoy Pat

achrimsd... said...

Plumb
Gypsum
Paper and paint

Kernow Lover said...

password must exclude the walls repair, paving the way for tiles, etc. to give the walls a coat of paint mist and then into the kitchen, you can determine the thickness of the soil does not allow for the height of the counter, or difficulty having Shutouts.